The modern Kingstown Port is on track to be fully operational by mid-2025, with 82% of construction already completed. According to Minister of Finance Hon. Camillo Gonsalves, the project has significantly impacted the local economy, directly retaining $95 million through local purchases and salaries, with subcontractor activities contributing even more. Currently, 169 Vincentians are employed on the site.

    The 2025 Budget has allocated $92.6 million to finalize the port’s completion. Key tasks for this phase include:

    • Building a container freight station.
    • Constructing administrative and maintenance workshop buildings with interior finishing, elevators, and solar panels.
    • Completing a maintenance garage and Break Bulk Warehouse.
    • Installing pavement and operational facilities.
    • Upgrading utilities, including potable water, sewer lines, and fire lines.
    • Landscaping and roadworks.
    • Commissioning and testing the entire facility.

    This state-of-the-art port aims to enhance Vincentian trade and connectivity while contributing to the local economy.